File #: R-2020-0220    Version: 1
Type: Resolution Status: Adopted
File created: 4/22/2020 In control: Public Works Committee
On agenda: 4/22/2020 Final action: 4/22/2020
Title: Resolution to approve bid of LaLonde Contractors, Inc. for the installation of concrete curb and gutter, concrete pavement, driveway replacement, sanitary sewer relay, storm sewer, building services and utility adjustments in W. Lakefield Ave. from E/O S. 119 St. to S. 122 St. and W. Euclid Ave. from S. 119 St. to S. Villa Ct. within the City of West Allis in the amount of $825,833.43 .
Sponsors: Public Works Committee
Attachments: 1. 2020-5 BID RESULTS, 2. Signed R-2020-0220 attachment.signed
title
Resolution to approve bid of LaLonde Contractors, Inc. for the installation of concrete curb and gutter, concrete pavement, driveway replacement, sanitary sewer relay, storm sewer, building services and utility adjustments in W. Lakefield Ave. from E/O S. 119 St. to S. 122 St. and W. Euclid Ave. from S. 119 St. to S. Villa Ct. within the City of West Allis in the amount of $825,833.43 .
body
WHEREAS, The Board of Public Works reports that it duly advertised for bids for the furnishing of certain materials and the performance of all work required for the improvements in a certain area as hereinafter described; that the bids received as shown on the attached bid report were reasonable and hereby recommends and deems it to be for the best interests of the City of West Allis that the bid of LaLonde Contractors, Inc. for 2020 Project No. 5 be accepted.

NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the bid of LaLonde Contrctors, Inc. for 2020 Project No. 5 for the installation of concrete curb and gutter, concrete pavement, driveway replacement, sanitary sewer relay, storm sewer, building services and utility adjustments in:
West Lakefield Avenue from E/O South 119th Street to South 122nd Street
West Euclid Avenue from South 119th Street to South Villa Court

(PLAN FILE NOS: SP-1251, SP1252, S-1626, S-1627, S-1628, U-2656, U-2657)
for the sum of Eight Hundred Twenty-Five Thousand, Eight Hundred Thirty-Three and 43/100 dollars ($825,833.43)
be accepted, and the proper City officers are hereby authorized and directed to enter into contractual relations with said contractor for the performance of said work, in accordance with the prices submitted in their proposal and with the specifications of the City of West Allis, and that all other bids received for same be rejected; and,

BE IT FURTHER RESOLVED That said improvements be installed with funding from Sanitary Sewer Funds, Storm Water Management Funds, Water Utility F...