File #: R-2018-0274    Version: 1
Type: Resolution Status: Adopted
File created: 5/1/2018 In control: Public Works Committee
On agenda: 5/1/2018 Final action: 5/1/2018
Title: Resolution accepting work of Globe Contractors, Inc. for the installation of concrete curb and gutter, concrete pavement, miscellaneous walk repair, driveway replacement, sanitary sewer relay, storm sewer, storm sewer relay, water main relay, building services and utility adjustments in W. Hicks St. from S. 76 St. to S. 81 St., S. 80th St. from W. Hicks St. to W. Rogers St. and S. 81st St. from W. Becher St. to W. Grant St. in the City of West Allis and authorizing and directing settlement of said contract in accordance with contract terms for final payment of 2014 Project No. 5 in the amount of $10,000.00 of the $2,598,895.23 total project cost.
Sponsors: Public Works Committee
Attachments: 1. R-2018-0274 signed

title

Resolution accepting work of Globe Contractors, Inc. for the installation of concrete curb and gutter, concrete pavement, miscellaneous walk repair, driveway replacement, sanitary sewer relay, storm sewer, storm sewer relay, water main relay, building services and utility adjustments in W. Hicks St. from S. 76 St. to S. 81 St., S. 80th St. from W. Hicks St. to W. Rogers St. and S. 81st St. from W. Becher St. to W. Grant St. in the City of West Allis and authorizing and directing settlement of said contract in accordance with contract terms for final payment of 2014 Project No. 5 in the amount of $10,000.00 of the $2,598,895.23 total project cost.

body

WHEREAS, Globe Contractors, Inc. has completed their contractual obligations in accordance with the plans and specifications therefore, attested by the approval for payment by the Interim City Engineer.

 

NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the work of Globe Contractors,, Inc. for 2014 Project No. 5 for the installation of concrete curb and gutter, concrete pavement, miscellaneous walk repair, driveway replacement, sanitary sewer relay, storm sewer, storm sewer relay, water main relay, building services and utility adjustments in:

 

West Hicks Street from South 76 Street to South 81 Street

South 80th Street from West Hicks Street to West Rogers Street

South 81st Street from West Becher Street to West Grant Street

 

(PLAN FILE NOS. SP-1192, SP-1193, SP-1194, S-1508, S-1509, S-1510, S-1511,

S-1512,         S-1513, S-1514, U-2579, U-2580, U-2581, U-2582, W-1324, W-1325,

W-1326, W-1327, W-1328)

 

be and the same is hereby accepted, and the proper City officers are hereby authorized and directed to make settlement with the said contractor in accordance with terms of said contract.