File #: R-2018-0078    Version: 1
Type: Resolution Status: Adopted
File created: 2/6/2018 In control: Public Works Committee
On agenda: 2/6/2018 Final action: 2/6/2018
Title: Resolution authorizing the Interim City Engineer to amend an existing Contract with Harwood Engineering Consultants, Ltd. for Engineering Consulting Services related to the Phase 2 retrofitting of LED lighting in city buildings for an amount not to exceed $12,500.00.
Sponsors: Public Works Committee
Attachments: 1. Harwoord Documents, 2. R-2018-0078 signed, 3. signed agreement
Title
Resolution authorizing the Interim City Engineer to amend an existing Contract with Harwood Engineering Consultants, Ltd. for Engineering Consulting Services related to the Phase 2 retrofitting of LED lighting in city buildings for an amount not to exceed $12,500.00.
Body
WHEREAS, the City has an existing agreement with Harwood Engineering Consultants in the amount of $47,955.00 to perform an assessment of existing City facilities with regard to lighting types, quantities and electrical systems presently in use and to identify opportunities to replace existing lighting systems at various City buildings with LED technology and to prepare an energy reduction plan for each building that measures energy savings; and,
WHEREAS, Phase 1 of the LED light retrofitting is now complete at City Hall, the Senior Center, the Health Department, the Library, and Fire Station No. 2; and
WHEREAS, the City will need further assistance from Harwood Engineering Consultants, Ltd. to produce drawings of each facility for the Phase 2 light removals and additions at the Police Court Center, Fire Station No. 1, Fire Station No. 3 and Fire Administration Building. The City will also need assistance in producing specifications that can be used for bidding the procurement and installation of LED lighting equipment and in the review of shop drawing submittals and in the coordination with Focus on Energy for Bonus Rebates.
NOW, THEREFORE, BE IT RESOLVED, by the Mayor and Common Council of the City of West Allis that the proposal dated January 23, 2018 submitted by Harwood Engineering Consultants, Ltd. for furnishing Engineering Consulting Services related to retrofitting LED lighting in city buildings for an amount not to exceed $12,500.00 be and is hereby accepted.
BE IT FURTHER RESOLVED That funds for this purchase are available in the Buildings & Facilities Capital Projects Fund budget, and the purchase will be charged to Account Number 354-6051-517-3101, Public Works Project Ac...

Click here for full text