title
Resolution accepting work of MJ Construction, Inc. for the installation of sanitary sewer relays and backyard storm sewer in various locations in the City of West Allis and authorizing and directing settlement of said contract in accordance with contract terms of 2008 Project No. 14.
body
WHEREAS, MJ Construction, Inc. has completed their contractual obligations in accordance with the plans and specifications therefore, attested by the approval for payment by the City Engineer.
NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the work of:
MJ Construction, Inc. - 2008 Project No. 14
for the installation of sanitary sewer relays and backyard storm sewer in:
South 54th Street from West Rogers Street to West Mobile Street,
South 97th Street from West Schlinger Avenue to West Washington Street,
Easement 745' N. of West Grant St. from South 96th St. to 160' W. of South 96th St.,
West Eckel Lane from South 85th Street to South 88th Street
be and the same is hereby accepted, and the proper City officers are hereby authorized and directed to make settlement with the said contractor in accordance with terms of said contract.