Title: Resolution accepting work of Wolf Paving Co., Inc. for the street construction & utility adjustments at W. Becher St from S. 92nd St. to S. 99th St. in the City of West Allis and authorizing and directing settlement of said contract in accordance with contract terms of 2022 Project No. 14 for final payment in the amount of $2,000.
Sponsors: Public Works Committee
Attachments: 1. Res_R-2025-0007, 2. Res_R-2025-0007 SIGNED

title

Resolution accepting work of Wolf Paving Co., Inc. for the street construction & utility adjustments at W. Becher St from S. 92nd St. to S. 99th St. in the City of West Allis and authorizing and directing settlement of said contract in accordance with contract terms of 2022 Project No. 14 for final payment in the amount of $2,000.

 

body

WHEREAS, Wolf Paving Co., Inc. has completed their contractual obligations in accordance with the plans and specifications therefore, attested by the approval for payment by the City Engineer.

 

NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the work of:

Wolf Paving Co., Inc.  - 2022 Project No.14

 

for the asphalt resurfacing of the pavement, including miscellaneous concrete sidewalk repair, landscaping, and utility adjustments in:

 

W. Becher St. from S. 92nd St. to S. 99th St.

 

be and the same is hereby accepted, and the proper City officers are hereby authorized and directed to make settlement with the said contractor in accordance with terms of said contract.

 

Recommendation