WHEREAS, W. Greenfield Ave. from S. 84th St. to S. 62nd St. and W. National Ave. from S. 62nd to S. 56th St. are designated a state truck connecting highway; and,
WHEREAS, WisDOT monetarily assists the City to maintain the connecting highway street through quarterly payments per lane mile with Connecting Highway Aids; and,
WHEREAS, W. Greenfield Ave. from S. 84th St. to S. 62nd St. and W. National Ave. from S. 62nd to S. 56th St. is in very poor condition with the overlying asphalt being worn and cracked and the base concrete being heaved and cracked extensively as well; and,
WHEREAS, W. Greenfield Ave. was originally built with concrete pavement in 1955 and resurfaced in 1992; and,
WHEREAS, the WisDOT has notified the City that the connecting highway is due for a reconstruction at the state's expense for construction with cost shares for design, parking, lighting, sidewalk, and streetscaping, and,
WHEREAS, the WisDOT agreed to divided the 1.75 miles into three (3) separate projects of S. 84th St. to S. 76th St.; S. 76th St. to S. 70th St.; and S. 70th St. to S. 56th St., tentatively scheduled for construction 2030 through 2032 depending on state funding and the I-94 E/W Freeway project, and,
WHEREAS, the State/Municipal Agreement includes the following major items; Plan Development, Real Estate Acquisition and Construction for the street pavement, traffic signals, storm sewer, and any other incidental street construction impacts.
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of West Allis that the City Engineer be and is hereby authorized and directed to enter into an agreement with the Wisconsin Department of Transportation for the Projects (State IDs 2230-05-02, 2230-05-03, and 2230-05-04), copies of the State/Municipal Agreements are attached hereto an...