Resolution accepting work of Musson Bros., Inc. for the installation of connection liners in the sanitary sewer system at various locations and authorizing final payment in the amount of $2,000 for 2020 Project No. 14.
body
WHEREAS, Musson Bros., Inc. has completed their contractual obligations in accordance with the plans and specifications therefore, attested by the approval for payment by the City Engineer.
NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the work of:
Musson Bros., Inc. for the installation of connection liners in the sanitary sewer system at:
Various Locations within the City of West Allis
PLAN FILE NOS. X-911
be and the same is hereby accepted, and the proper City officers are hereby authorized and directed to make settlement with the said contractor in accordance with terms of said contract.