File #: R-2019-0059    Version: 1
Type: Resolution Status: Adopted
File created: 2/5/2019 In control: Public Works Committee
On agenda: 2/5/2019 Final action: 2/5/2019
Title: Resolution to confirm and adopt the report of the City Engineer containing the schedule of proposed assessments for improvement of S. 75 Street from North of W. Walker Street to W. Washington Street, S. 80 Street from W. Greenfield Avenue to W. National Avenue and portions of intersecting streets.
Sponsors: Public Works Committee
Attachments: 1. R-2019-0059 signed, 2. Engineering Packet
title
Resolution to confirm and adopt the report of the City Engineer containing the schedule of proposed assessments for improvement of S. 75 Street from North of W. Walker Street to W. Washington Street, S. 80 Street from W. Greenfield Avenue to W. National Avenue and portions of intersecting streets.
body
WHEREAS, The City Engineer, pursuant to Preliminary Resolution No. R-2018-0672, adopted on November 5, 2018, prepared and submitted his report as provided in sec. 66.0703(5) of the Wisconsin Statutes, for the improvement of the streets as hereinafter described; and,

WHEREAS, The City Clerk gave due notice that such report was open for inspection at his office and also at the office of the City Engineer, and that all persons interested could appear before the Common Council and be heard concerning the matters contained in the Preliminary Resolution and Report; and,

WHEREAS, The Common Council met pursuant to such notice, at the time and place therein named; and having considered all statements and communications concerning the proposed improvements, relating to the matters contained in the City Engineer's report, including the schedule of proposed assessments, the Common Council makes no change in said report.

NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis:

1. The report of the City Engineer, including the schedule of the proposed assessments, for the improvement of S. 75 Street from North of W. Walker Street to W. Washington Street, S. 80 Street from W. Greenfield Avenue to W. National Avenue and portions of intersecting streets by concrete reconstruction, new concrete sidewalk, new driveway approaches, storm sewer, storm sewer relay, sanitary sewer relay, water main relay, building services and utility adjustments be and the same is hereby approved and adopted.

2. The property against which the assessments are proposed is benefited; the assessments shown on the report are true and correct, have been determined on a rea...

Click here for full text