File #: R-2008-0082    Version: 1
Type: Resolution Status: Adopted
File created: 3/31/2008 In control: Public Works Committee
On agenda: Final action: 3/31/2008
Title: Resolution to approve bid of Underground Pipeline Construction, Inc. for installation of water main relay and building services in W. Greenfield Avenue from S. 60 Street to S. 62 Street, in the amount of $73,198.00.
Sponsors: Public Works Committee
Attachments: 1. R-2008-0082 Packet Doc

title

Resolution to approve bid of Underground Pipeline Construction, Inc. for installation of water main relay and building services in W. Greenfield Avenue from S. 60 Street to S. 62 Street, in the amount of $73,198.00.

body

WHEREAS, The Board of Public Works reports that it duly advertised for bids for the furnishing of certain materials and the performance of all work required for the improvements in a certain area as hereinafter described; that the bids received as shown on the attached bid report were reasonable and hereby recommends and deems it to be for the best interests of the City of West Allis that the bid of Underground Pipeline Construction, Inc. for 2008 Project No. 5  be accepted.

 

NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the bid of Underground Pipeline Construction, Inc. for 2008 Project No. 5:

 

Water Main Relay and Building Services  in W. Greenfield Avenue from S. 60 Street to S. 62 Street

(Plan File No(s). W-1238)

 

for the sum of  Seventy-three thousand, one hundred ninety-eight dollars even ($73,198.00)

 

be accepted, and the proper City officers are hereby authorized and directed to enter into contractual relations with said contractor for the performance of said work, in accordance with the prices submitted in their proposal and with the specifications of the City of West Allis, and that all other bids received for same be rejected; and,

 

BE IT FURTHER RESOLVED That said improvements be installed with funding by Water Utility Funds.