title
Resolution accepting work of Globe Contractors, Inc. for the installation of concrete curb and gutter, concrete pavement, concrete sidewalk, driveway replacement, sanitary sewer relay, storm sewer, storm sewer relay, water main relay, building services and utility adjustments in South 119th Street from West Oklahoma Avenue to West Ohio Avenue in the City of West Allis and authorizing and directing settlement of said contract in accordance with contract terms for final payment of 2016 Project No. 11 in the amount of $23,686.80 of the $1,147,133.90 total project cost.
body
WHEREAS, Globe Contractors, Inc. has completed their contractual obligations in accordance with the plans and specifications therefore, attested by the approval for payment by the Director of Public Works/City Engineer.
NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the work of:
Globe Contractors, Inc. - 2016 Project No. 11
for the installation of concrete curb and gutter, concrete pavement, concrete sidewalk, driveway replacement, sanitary sewer relay, storm sewer, storm sewer relay, water main relay, building services and utility adjustments in:
South 119th Street from West Oklahoma Avenue to West Ohio Avenue
(PLAN FILE NOS. SP-1221, S-1564, S-1565, W-1349,
W-1350, U-2617, U-2618)
be and the same is hereby accepted, and the proper City officers are hereby authorized and directed to make settlement with the said contractor in accordance with terms of said contract.