File #: R-2005-0183    Version: 1
Type: Resolution Status: Adopted
File created: 6/7/2005 In control: Public Works Committee
On agenda: Final action: 6/21/2005
Title: Resolution to approve bid of Capitol Pavers, Inc. for street construction, sanitary sewer relay, storm sewer, building services and utility adjustments in S. 119 St. from W. Ohio Ave. to W. Morgan Ave. and S. 123 St. from 395' south of W. Euclid Ave. to W. Ohio Ave., in the amount of $620,054.
title
Resolution to approve bid of Capitol Pavers, Inc. for street construction, sanitary sewer relay, storm sewer, building services and utility adjustments in S. 119 St. from W. Ohio Ave. to W. Morgan Ave. and S. 123 St. from 395' south of W. Euclid Ave. to W. Ohio Ave., in the amount of $620,054.
body
WHEREAS, The Board of Public Works reports that it duly advertised for bids for the furnishing of certain materials and the performance of all work required for the improvements in a certain area as hereinafter described; that the bids received as shown on the attached bid report were reasonable and hereby recommends and deems it to be for the best interests of the City of West Allis that the bid of Capitol Pavers Inc. for 2005 Project No. 12 be accepted.
 
NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the bid of Capitol Pavers Inc. for 2005 Project No. 12:
 
Street Construction, Sanitary Sewer Relay, Storm Sewer,
Building Services & Utility Adjustments
 
S. 119 St. from W. Ohio Ave. to W. Morgan Ave. and
S. 123 St. from 395' south of W. Euclid Ave. to W. Ohio Ave.
(Plan File No(s). SP-1100, SP-1101, U-2391, U-2392, S-1293)
 
for the sum of Six Hundred Twenty Thousand, Fifty-Four Dollars ($620,054)
 
be accepted, and the proper City officers are hereby authorized and directed to enter into contractual relations with said contractor for the performance of said work, in accordance with the prices submitted in their proposal and with the specifications of the City of West Allis, and that all other bids received for same be rejected; and,
 
BE IT FURTHER RESOLVED That said improvements be installed with funding by Bond Funds, Water Utility Funds, Sanitary Sewer Funds, Storm Water Management Funds and Special Assessments.
 
Eng05-51