Resolution accepting work of Lalonde Contractors for street construction and authorizing and directing settlement of said contract in accordance with contract terms of 2022 Project No. 4 for final payment in the amount of $800.
body
WHEREAS, Lalonde Contractors has completed their contractual obligations in accordance with the plans and specifications therefore, attested by the approval for payment by the City Engineer.
NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the work of:
Lalonde Contractors - 2022 Project No.4
Street construction, sanitary sewer relay, storm sewer relay, water main relay, building services, green infrastructure installation and utility adjustments:
W. Mitchell St. from S. 92nd St. to S. 96th St.
.
be and the same is hereby accepted, and the proper City officers are hereby authorized and directed to make settlement with the said contractor in accordance with terms of said contract.
Recommendation
Adopt