WHEREAS, the initial project funding approved by SEWRPC in the last biennium was limited to $4,470,309 in federal funding and did not cover the entire 80% cost share of the design and construction cost for the W. National Ave. project; and,
WHEREAS, the original State/Municipal Agreement was entered into after council approved Resolution 2023-0112 on February 7, 2023 that contained the preliminary funding numbers so that design efforts could begin; and,
WHEREAS, the WisDOT has notified the City that this project has been fully funded in the current biennium resulting in federal funding of $12,482,880 for the 80% cost share for design and construction; and,
WHEREAS, the State/Municipal Agreement has been revised to reflect the federal funding increase and the most recent cost estimate information; and,
WHEREAS, the W. National Ave. project from S. 95th St. to S. 108th St. is scheduled for construction in 2026.
NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the City Engineer be and is hereby authorized and directed to enter into an agreement with the WisDOT for the Project (State ID 2410-15-00/70/71), a copy of the State/Municipal Agreement is attached hereto and by reference made a part hereof.
BE IT FURTHER RESOLVED that the total eligible estimated design project cost is $20,254,600 of which $12,482,880 is anticipated to be the Federal share and the remaining $7,771,720 is anticipated to be the local municipal share which includes $4,295,000 for sanitary sewer and watermain relays.
BE IT FURTHER RESOLVED that funds for this reconstruction project on W. National Ave. are budgeted and available in the Bond Funds, Capital Project cash reserves (future reimbursement from special assessments), ...