Title: Resolution accepting work of State Contractors, Inc. for the removal and reconstruction of the concrete alley pavement, storm sewer, storm sewer relay, utility adjustments and storm underdrain in various locations within the City of West Allis and authorizing and directing settlement of said contract in accordance with contract terms of 2013 Project No. 6.
Sponsors: Public Works Committee
title
Resolution accepting work of State Contractors, Inc. for the removal and reconstruction of the concrete alley pavement, storm sewer, storm sewer relay, utility adjustments and storm underdrain in various locations within the City of West Allis and authorizing and directing settlement of said contract in accordance with contract terms of 2013 Project No. 6.
body
WHEREAS, State Contractors, Inc. has completed their contractual obligations in accordance with the plans and specifications therefore, attested by the approval for payment by the Director of Public Works/City Engineer.

NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the work of State Contractors, Inc. - 2013 Project No. 6 for the removal and reconstruction of the concrete alley pavement, storm sewer, storm sewer relay, utility adjustments and storm underdrain in:

1. North/South alley between S. 74 St. and S. 75 St.: W. Washington St. to W. Madison St.
PLAN FILE NOS. AP-450 & U-2549
2. (INTENTIONALLY OMMITTED)
3. East/West alley between S. 71 St. and S. 72 St.: W. Greenfield Ave. to W. Orchard St.
PLAN FILE NOS. AP-452 & U-2550
4. East/West alley between S. 75 St. and S. 76 St.: W. Madison St. to W. Greenfield Ave.
PLAN FILE NOS. AP-453 & U-2551
5. North/South and East/West alley between S. 73 St. and S. 74 St.: W. Greenfield Ave. to W. Orchard St. PLAN FILE NOS. AP-454 & U-2550
6. North/South and East/West alley between S. 57 St. and S. 58 St.: W. National Ave. to W. Greenfield Ave. PLAN FILE NOS. AP-455 & U-2552
7. North/South alley between S. 62 St. and S. 63 St.: W. Mineral St. to W. Washington St.
PLAN FILE NOS. AP-456 & U-2553
8. North/South alley between S. 60 St. and S. 61 St.: W. Hayes Ave. to W. Arthur Ave.
PLAN FILE NOS. AP-457 & U-2554
9. North/South and East/West alley between S. 56 St. and S. 57 St.: W. National Ave. to W. Greenfield Ave. PLAN FILE NOS. AP-458 & U-2555
10. North/South & East/West alley btwn S. 70 St. & S. 7...