title
Resolution accepting work of UPI, LLC for street construction in S. 80 St. from W. Grant St. to W. Lincoln Ave. and S. 87 St. from W. Harrison Ave. to the dead end and authorizing settlement of said contract in accordance with contract terms for final payment of 2019 Project No. 7 in the amount of $2,000
body
WHEREAS, UPI, LLC has completed their contractual obligations in accordance with the plans and specifications therefore, attested by the approval for payment by the City Engineer.
NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the work of:
UPI, LLC - 2019 Project No. 7
installation of concrete curb and gutter, concrete pavement, concrete sidewalk, driveway replacement, sanitary sewer relay, storm sewer, storm sewer relay, water main relay, building services, and utility adjustments in:
South 80th Street from West Grant Street to West Lincoln Avenue
South 87th Street from West Harrison Avenue to Dead End
(PLAN FILE NOS. SP-1248, SP-1249, S-1618, U-2644, W-1388, X-898)
be and the same is hereby accepted, and the proper City officers are hereby authorized and directed to make settlement with the said contractor in accordance with terms of said contract.