File #: R-2016-0046    Version: 1
Type: Resolution Status: Adopted
File created: 3/1/2016 In control: Public Works Committee
On agenda: 3/1/2016 Final action: 3/1/2016
Title: Resolution to approve bid of MJ Construction, Inc., for the installation of concrete curb and gutter, concrete pavement, miscellaneous walk repair, driveway replacement, sanitary sewer relay, storm sewer, storm sewer relay, water main relay, building services and utility adjustments in S. 79th St. from W. Greenfield Ave. to W. National Ave. and S. 85th St. from W. Washington St. to W. Greenfield Ave. in the City of West Allis in the amount of $1,997,834.50.
Sponsors: Public Works Committee
Attachments: 1. 2016 Prj 1 Bid 2-25-16, 2. R-2016-0046 signed resolution
Related files: 2016-0134, 2016-0091, 2016-0088

title

Resolution to approve bid of MJ Construction, Inc., for the installation of concrete curb and gutter, concrete pavement, miscellaneous walk repair, driveway replacement, sanitary sewer relay, storm sewer, storm sewer relay, water main relay, building services and utility adjustments in S. 79th St. from W. Greenfield Ave. to W. National Ave. and S. 85th St. from W. Washington St. to W. Greenfield Ave. in the City of West Allis in the amount of $1,997,834.50.

body

WHEREAS, The Board of Public Works reports that it duly advertised for bids for the furnishing of certain materials and the performance of all work required for the improvements in a certain area as hereinafter described; that the bids received as shown on the attached bid report were reasonable and hereby recommends and deems it to be for the best interests of the City of West Allis that the bid of MJ Construction, Inc. for 2016 Project No. 1 be accepted.

 

NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the bid of MJ Construction, Inc., for 2016 Project No. 1 for the installation of concrete curb and gutter, concrete pavement, miscellaneous walk repair, driveway replacement, sanitary sewer relay, storm sewer, storm sewer relay, water main relay, building services and utility adjustments in:

 

South 79th Street from West Greenfield Avenue to West National Avenue

South 85th Street from West Washington Street to West Greenfield Avenue

 

PLAN FILE NOS. SP-1217, SP-1220, X-853, X-854, S-1553, S-1554, S-1555, W-1340, W-1341, W-1342, W-1343, W-1344, U-2603, U-2604, U-2605, U-2606, U-2607

 

for the sum of One Million, Nine Hundred Ninety-Seven Thousand, Eight Hundred Thirty-Four and 50/100 dollars ($1,997,834.50)

 

be accepted, and the proper City officers are hereby authorized and directed to enter into contractual relations with said contractor for the performance of said work, in accordance with the prices submitted in their proposal and with the specifications of the City of West Allis, and that all other bids received for same be rejected; and,

 

BE IT FURTHER RESOLVED That said improvements be installed with funding by Sanitary Sewer Funds, Storm Water Management Funds, Water Utility Funds, Bond Funds and Funds from Special Assessments.