Resolution to approve bid for alley reconstruction in various locations in the City of West Allis, in the amount of $807,854.10.
body
WHEREAS, The Board of Public Works reports that it duly advertised for bids for the furnishing of certain materials and the performance of all work required for the improvements in a certain area as hereinafter described; that the bids received as shown on the attached bid report were reasonable and hereby recommends and deems it to be for the best interests of the City of West Allis that the bid of Capitol Pavers for 2003 Project No. 4 be accepted.
NOW, THEREFORE, BE IT RESOLVED By the Common Council of the City of West Allis that the bid of Capitol Pavers for 2003 Project No. 4 - Alley Reconstruction in:
East/West alley between S. Buchanan Pl., the dead end east, W. Stuth Pl. and W. Beloit Rd.
PLAN FILE NOS. AP-310 & U-2323
East/West alley between S. Buchanan Pl., S. 72 St., W. Stuth Pl. and W. Beloit Rd.
PLAN FILE NOS. AP-311 & U-2324
North/South alley between S. 76 St., S. 77 St., W. Greenfield Ave. and W. Orchard St.
PLAN FILE NOS. AP-312 & U-2325
North/South and East/West alleys between S. 56 St., S. 57 St., W. Lincoln Ave. and W. Hayes Ave.
PLAN FILE NOS. AP-313 & U-2326
North/South and East/West alleys between S. 57 St., S. 58 St., W. Lincoln Ave. and W. Hayes Ave.
PLAN FILE NOS. AP-314 & U-2327
North/South and East/West alleys between S. 68 St., S. 69 St., W. Grant St. and W. Lincoln Ave.
PLAN FILE NOS. AP-315 & U-2328
North/South alley between S. 68 St., S. 69 St., W. Becher St. and W. Grant St.
PLAN FILE NOS. AP-316 & U-2329
East/West alley between S. 73 St., S. 74 St., W. Lapham St. and W. National Ave.
PLAN FILE NOS. AP-317 & U-2330
North/South and East/West alleys between S. 65 St., S. 66 St., W. Revere Pl. and W. Beloit Rd.
PLAN FILE NOS. AP-318 & U-2331
East/West alley between S. Livingston Terr., S. 67 Pl., W. Grant St. and W. Beloit Rd.
PLAN FILE NOS. AP-319 & U-2332
East/West alley between W. McGeoch Ave., S. 65 St., W. Revere Pl. and W. Oconto Pl.
PLAN FILE NOS. AP-320 & U-2333
North/South and East/West alleys between S. 77 St., S. 78 St., W. Rogers St. and W. Becher St.
PLAN FILE NOS. AP-321 & U-2334
North/South alley between S. 70 St., S. 71 St., W. Madison St. to 240 ft. south
PLAN FILE NOS. AP-322 & U-2335
for the removal and reconstruction of the concrete alley pavement, storm sewer, utility adjustments and storm underdrain
for the sum of Eight Hundred Seven Thousand, Eight Hundred Fifty-four Dollars and Ten Cents ($807,854.10)
be accepted, and the proper City officers are hereby authorized and directed to enter into contractual relations with said contractor for the performance of said work, in accordance with the prices submitted in their proposal and with the specifications of the City of West Allis, and that all other bids received for same be rejected; and,
BE IT FURTHER RESOLVED That said improvements be installed with funding by Bond Funds, Storm Water Management Funds and Special Assessments.
Eng03-54